Page tree

You can reactivate a task that you previously made inactive.

Requirements: You must have a project role that includes the Admin Tasks user right.

You might want to reactivate a task if you accidentally inactivated the task before it was complete or if the reason for inactivating the task has changed—for example, you inactivated a task because the element was removed from a layout, but the element is now back in the layout.

Tip: To view all active tasks, in the Filter list, select All Active.

  1. In the Tasks view, in the Filter list, select All inactive.
    All inactive tasks appear.
  2. Select the task that you want to reactivate, and from the Tasks menu, select Set Active/Inactive State.
    The task disappears from the list of inactive tasks and appears in the list of active tasks.