    You set processing priority in the Start Process dialog box when you initiate a process, but you can change the priority of the process in Queue Manager.

    1. Open Queue Manager.
    2. View the specific process in one of these ways:
      • To select a JTP process, click the JTP Queues tab, and select a JTP in the list.
      • To select a process by type, click the Process Types tab, and select a process type in the list.
    3. In the View pane, select the process that you want to change.
    4. From the Edit menu, select Process > Select Task Priority.
    5. In the Select Task Priority dialog box, select the desired priority and click Select.

    The new priority appears in the Priority column of the View pane.
    A new history detail is also created to record the change in priority. History details for a job can be viewed in the History view of Job Manager.